Our Process
Your Path Forward
"Unlocking your vision begins with understanding your unique needs and aspirations. Through a collaborative and iterative design process, we transform ideas into inspiring spaces tailored just for you."
Step 1
Design
(4-8 Weeks)
Step 2
Permitting
(4-8 Weeks)
Step 3
Construction
(4-8 Weeks)
Step-01 Getting Started
GSADUs:
- Conduct “Initial Walkthrough Meeting”
- Survey Existing Site Conditions & Inform on Feasibility
- Explore Financing Option(s)
- Conduct “Design Programming Q&A”
- Assign Estimator & Define Scope of Work
- Generate Proposal
- Complete Client On-boarding
Clients:
- Inquire & Schedule “Initial Walkthrough Meeting”
- Complete “Design Programming Q&A”
- Qualify for Financing
- Sign Proposal
- Submit Deposit
1-2 Weeks

Step-02 Design
GSADUs:
- Initiate Design & Engineering Process
- Generate Construction Documents
- Address Client Revisions
Clients:
- Select & Approve Design
- Provide Feedback
- Approve Final Design Document(s)
- Administer Progress Payment(s)
4-8 Weeks

Step-03 Permitting
GSADUs:
- Submit Project for Permitting
- Maintain Document Control
- Receive Approved Permit(s)
- Update Construction Contract
- Generate Construction Schedule
Clients:
- Submit Permit Fees
- Sign Contract Amendment (As Incurred)
- Administer Progress Payments
4-8 Weeks

Step-04 Construction
GSADUs:
- Conduct “Pre-Construction Meeting”
- Start Construction Process
- Administer Inspections w/ Building Dept.
- Conduct Periodic Trade Work
- Inspections w/ Client
- Complete Final Punchlist
- Close-Out Project
Clients:
- Review & Approve Design Development
- Provide Feedback
- Administer Progress Payment(s)
- Provide Final Punchlist
- Approve & Sign Project Completion Form
4-8 Weeks
Project Schedule Summary
Schedule describing how long it takes to complete our standard services on the following project types.

Design:
-/- (1 to 2 months)

Permitting:
-/- (1 to 2 months)

Construction:
-/- (3 to 5 months)